Contracts & partnershipsNov 9, 2026 · 7:11 PM ET

Bitzero receives electrical equipment for Norway data center

Bitzero Holdings announced the arrival of two 60 MVA transformers at its flagship data center site in Namsskogan, Norway. This completes the high-voltage long-lead equipment package to expand the site to up to 110 megawatts. Additionally, the company engaged investor relations provider Barchart for a 90-day term costing $120,000.

  • Arrival of transformers completes equipment package for up to 110 MW expansion
  • Company engaged Barchart for investor relations services at $40,000 per month
Read the SEC filing ↗Form 6-K, filed Nov 10, 2026